High School Classrooms- Everett, MA


The Situation:

Everett HS was built in 2007 with T8 lamps and ballasts. The existing fluorescent system was coming to its end of useful life and Everett Unified School District was planning on spending maintenance funds to re-lamp and re-ballast an entire 5 story high school. The existing light fixtures were only eight years old so the school district did not want to remove expensive architectural direct/ indirect luminares. The school district considered keeping the existing fluorescent lighting system, but they were drawn to LED BAR because of the dramatic reduction in operating cost will allow funds to be spent in other criCase Study- School Districttical areas that were not in budget.

Download the Case Study